The project
A distribution centre consisting of three warehouses has been built in the port area of Ghent. Soil improvement using gravel columns was carried out for two warehouses with a total floor area of 40,464 m².

The challenges
This project was very challenging. It involved a large floor area, a tight schedule and activities by third parties. All this was combined with the logistics and storage of the aggregate material to be used.

The solution
By effectively integrating implementation knowledge and experience from surrounding projects into the implementation design during the design phase, Keller devised a highly feasible and cost-effective solution for the client.
The combination of an optimised design and a highly motivated team of employees resulted in a project that was completed on schedule and within budget, and a satisfied client.