A new high-power charging site has been delivered in the municipality of Tielt-Winge, Belgium, supporting the rapid expansion of eMobility across the region. Developed in collaboration with TotalEnergies, the site is designed to combine performance, reliability, and scalability.
The EPC scope included the delivery and installation of a 630 kVA high-voltage substation, the integration of three Alpitronic hyperchargers, and the complete electrotechnical works required to bring the site online. Each element was executed to ensure maximum uptime and to provide capacity for future growth.
The project came together through strong collaboration between multiple partners: Provoost Engineering for design, Lantzerath Belgium for civil works, Publisign for canopy design, and Frederik Roeges as project manager overseeing delivery on site.
This site is a clear example of how high-power charging infrastructure is built without compromise. With the right expertise and partnerships in place, Europe’s charging network is expanding at speed — ensuring the performance and resilience needed to power the energy transition.